Only 15pc progress on Ring Road project: SIGAR

· 2 min read · 308 views

KABUL (SIGAR) said on Wednesday.

Since 2006, the 233-kilometer segment of the Afghanistan's Ring Road between Qaisar and Laman has been funded by five separate grants from the Asian Development Bank totaling $721 million.

In a review, SIGAR said as of September 2017, the Afghan Ministry of Public Works (MoPW) had disbursed $249 million of the ADB grant funds to build this section of the road, but contractors had only achieved 15 percent construction progress.
From March 2014 through September 2017, no physical progress . . .