KANDAHAR CITY (Pajhwok): Factory owners in southern Kandahar province complain of snail-paced work on a 10 MW solar power project, saying the scheme is not being implemented the way the government has promised.
Work on the project was launched in September 2017 after three years of delay. Its completion was promised within a year. But 11 months on, construction of retaining walls and land preparation could not be completed.
USAID has provided $10 million while the Zolarestan Company, the contractor, is investing $9 million in the . . .